Redcrest Repowering Project - Edison, California

California, 16.6 MW

Redcrest Repowering Project

The 16.6 MW Redcrest repowering project in Edison, California, modernized an aging site through the installation of 10 SMA Sunny Central inverters. The upgrade extended the project’s operational lifetime, introduced advanced technology and restored long-term system reliability.

A leading U.S. hyperscale solar developer selected Sunny Central inverters after the site’s original equipment manufacturer exited the market, leaving the project with unsupported equipment, limited-service options and increased operational risk. SMA provided a reliable path forward with a modern solution that combined addvanced grid-support capabilities and flexible output voltage to meet evolving system requirements while ensuring long-term serviceability.

In addition, the Sunny Central inverters enabled the reuse of existing transformers, simplifying the repowering process, reducing installation complexity and minimizing project downtime.

Learn more about Repowering

Location
Edison, California


Commissioning
June 2025

System Size
16.6 MW AC


Estimated Annual CO2 Offset
~17,000 MT

SMA System Technology

10 x SMA Sunny Central

Learn more about Repowering

Modernize power plants

Questions? Speak to an SMA expert.